Activities

Major Planned Activities

Phase I : July 2007-March 2008

  • Survey on the Current Condition of Existing Small Water Supply Projects
    (Organization and Technology Analysis)
  • Survey on the Current Condition of Existing Small Water Supply Projects
    (Water Supply Facility and Hydrogeology)
  • Survey on the Condition of Operation and Maintenance
  • Analysis on Groundwater Recharge and Water Balance
  • Evaluation of Water Resources Potential
  • Preparation of Hydrogeological Map (OJT)
  • Establishment of Well/Geology GIS Database
  • Establishment of Database
  • Preparation of Draft of Implementation Guideline for Small Water Supply Project
  • Identification of Training Needs, and Formulation of Training Program

Phase II : April 2008-September 2009

  • Conduct of Training on Groundwater Development
  • Conduct of Training on Community Organizing for Operation and Maintenance
  • Plan of the Selection of Pilot Project Sites for Small Water Supply Projects
  • Plan of Water Source and Facility
  • Planning on Operation and Maintenance
  • Organization and Institutional Improvement Program
  • Preparation of Community Enhancement Action Plan
  • Formulation of Implementation Plan, Detailed Design, Cost Estimate and Site Selection
  • Implementation of Pilot Projects
  • Monitoring and Evaluation of Pilot Projects

Phase III : October 2009-June 2010

  • Compilation of the Output of the Project
  • Terminal Evaluation
  • Preparation and Submission of Project Completion Report
  • Conduct of Seminar

Record of Activities

DATE
ACTIVITIES
 
01/08/2007
JICA experts arrived at Manila
02/08/2007 The JICA experts moved to Davao.
03/08/2007
Kick-off Meeting (KOM) was held.
07-08/08/2007
1st field survey was conducted by DIDP staffs, LGU staffs and JICA experts in Davao City, Davao del Norte Province, Panabo City and Tagum City.
09/08/2007
1st technical transfer session was held in Davao City with attendance of the counterpart personnl from 9 LGUs.
14/08/2007
1st Joint Coordination Committee (JCC) for the Project was held in Davao City. Inception report was presented, mofification of Project Design Matrix (PDM) and Annual work plan for the first year were approved.
23-24/08/2007 2nd field survey was conducted in Davao Oriental Province, Digos City and Compostela Valley Province.
28/08/2007 2nd technical transfer session was held.
01/09/2007 Inventory survey started by sub-contractor.
05-06/09/2007 3rd field survey was conducted in Davao Oriental Province and Island Garden City of Samal (IGACOS)
11/09/2007 3rd technical transfer session was held.
12-13/09/2007 4th field survey was conducted in Davao del Norte and Compostela Valley Provinces.
19-20/09/2007 5th field survey was conducted in Davao del Sur Province and Davao City.
21/09/2007 GIS establishment was started by sub-contractor.
25/10/2007 4th technical transfer session was held.
26/10/2007 5th technical transfer session was held.
5-7/02/2008

Technical Transfer Session on Basic Concept of Community Organizing and Community Development. Community Needs Assessment , Community Organizing, Financial Management

04/2008 Orientation for extended Project Management Unit members.
13-14/05/2008 Training of Trainors on Community Orientation and Indentification of Potential Leaders. Training Presentation
16-20/06/2008 Electrical Prospecting Survey & Analysis Training.
19-20/06/2008 Phase 2- 1st Technical Transfer Session for Social Preparation and Community Organizaing.
25-27/06/2008 E.P. Survey at Brgy. Waan (DC/IGACOS)
2-3/07/2008 E.P. Survey at Brgy. Bangkal (Davao del Sur/Digos)
3-4/07/2008 Phase 2 - 2nd Technical Transfer Session for Social Preparation and Community Organizing.
8/07/2008 E.P. Survey at Brgy. Bangkal (Davao del Sur/Digos)
09-10/07/2008 E.P. Survey at Brgy. Alejal (Davao del Norte/Panabo)
15-18/07/2008

Basic Geology & Hydrogeology Lecture (1)Introduction to Geology, Geology of the Philippines Applications of Geology Historical Geology

22-25/07/2008 Basic Geology & Hydrogeology Lecture (2)
30/07-1/08/2008 E.P. Survey at Brgy. Bago (Oriental/Mati)
04/08/2008 Preliminary survey at Compostella project site
04-06/08/2008 Training of Trainors on Participatory Rural Appraisal & Team Building (Davao City and IGACOS PMU)
04-06/08/2008 E.P. Survey at Brgy. Cabidianan (Comval/Tagum)
04-05/08/2008 Preliminary survey at Brgy. Waan and lecture on planning with hydraulic calculations.
11/08/2008 Topographic survey at Brgy. Waan with Davao City and IGACOS.
11-13/08/2008 Training of Trainors on Participatory Rural Appraisal & Team Building (Davao del Sur and Digos City PMU)
11-15/08/2008 Topographic survey at Brgy. Waan with DIDP and Davao City GIS survey team.
13-15/08/2008 Training of Trainors on Participatory Rural Appraisal & Team Building (Davao del Norte, Compostella Valley, Tagum, Panabo City PMU)
14-15/08/2008 Training for survey and planning stage with Davao del Sur and Digos City
19/08/2008 E.P. Survey at Brgy. Alejal (Davao del Norte/Panabo)
19-20/2008 Discussion on the Final results of survey and start of the Design of supply system at Brgy. Waan.
20-21/08/2008 E.P. Survey at Brgy. Madua & Brgy. Nanyo (Panabo)
20-22/08/2008 Training of Trainors on Participatory Rural Appraisal & Team Building (Davao Oriental and Mati City PMU)
21-22/08/2008 Training for survey and planning stage with Davao del Norte and IGACOS
26-27/08/2008 Discussion on the progress of detailed Design of water supply system at Brgy.Waan.
26-29/08/2008

Training of Trainors on Basic Bawasa Orientation for Davao City, IGACOS, and Digos Ciy PMU

27-30/08/2008

E.P. Survey at Brgy. Bangkal (Davao del Sur/Digos)

28-29/08/2008 Training for survey and planning stage with Davao Oriental and Mati City.
01-02/09/2008 Finalization of the detailed design of Water supply system at Brgy.Waan with Davao City and IGACOS.
03/09/2008 E.P. Survey at Brgy. Cabidianan(Comval/Tagum)
03-04/09/2008 Training for survey and planning stage with ComVal and Tagum City
04/09/2008 E.P. Survey at Tagum City
05/09/2008 Consultation with Barangay Officials on the Final Design of the Water Supply system at Brgy. Waan.
05/09/2008 E.P. Survey at Brgy. Alejal (Davao del Norte/Panabo)
09-11/09/2008 Technical Sessions on Design Construction and Operation of Rural Water supply system with all LGU's.
10/09/2008 Training of Trainors on Basic Bawasa Orientation for Davao Oriental, Davao del Norte, Davao del Sur, ComVal, Tagum, Panabo and Mati Ciy PMU Bawasa Orientation

15-19/09/2008

 

Detailed Design of water supply system, Preparation of Plans, Detailed Drawing and Specifications, Preparation of Bill of Quantities and Cost Estimates, Preparation of Tender Bid Documents with Davao City and IGACOS.
16-18/09/2008 E.P. Survey at Mati City
22-26/09/2008 Detailed Design of water supply system, Preparation of Plans, Detailed Drawing and Specifications, Preparation of Bill of Quantities and Cost Estimates, Preparation of Tender Bid Documents with Davao City and IGACOS.
24-26/09/2008 E.P. Survey at Island Garden City of Samal
29-30/09/2008 Detailed Design of water supply system, Preparation of Plans, Detailed Drawing and Specifications, Preparation of Bill of Quantities and Cost Estimates, Preparation of Tender Bid Documents with Davao City and IGACOS.
30/09-03/10/2008 Training on practical alternative bookkeeping Training overview, Module 1, Module 2, Module 3, Module 4, Module 5, Module 6, Module 7, Module 8, Module 9, Module 10, Appendix
8-10/10/2008

Training on Basic Leadership A leader , 10 traits of a leader,planning skills