Phase I : July 2007-March 2008
- Survey on the Current Condition of Existing Small Water Supply Projects (Organization and Technology Analysis)
- Survey on the Current Condition of Existing Small Water Supply Projects (Water Supply Facility and Hydrogeology)
- Survey on the Condition of Operation and Maintenance
- Analysis on Groundwater Recharge and Water Balance
- Evaluation of Water Resources Potential
- Preparation of Hydrogeological Map (OJT)
- Establishment of Well/Geology GIS Database
- Establishment of Database
- Preparation of Draft of Implementation Guideline for Small Water Supply Project
- Identification of Training Needs, and Formulation of Training Program
Phase II : April 2008-September 2009
- Conduct of Training on Groundwater Development
- Conduct of Training on Community Organizing for Operation and Maintenance
- Plan of the Selection of Pilot Project Sites for Small Water Supply Projects
- Plan of Water Source and Facility
- Planning on Operation and Maintenance
- Organization and Institutional Improvement Program
- Preparation of Community Enhancement Action Plan
- Formulation of Implementation Plan, Detailed Design, Cost Estimate and Site Selection
- Implementation of Pilot Projects
- Monitoring and Evaluation of Pilot Projects
Phase III : October 2009-June 2010
- Compilation of the Output of the Project
- Terminal Evaluation
- Preparation and Submission of Project Completion Report
- Conduct of Seminar